Final | 4/13/2018 | 4/16/2018 | 4/16/2018 | A | PASS |
Chad Schwendiman
|
|
|
Inspection requested via web by MARGIE ROWE
|
Final | 4/12/2018 | 4/12/2018 | 4/12/2018 | P | FAIL |
Chad Schwendiman
|
|
|
Electrical has been. Ready for re inspection Inspection requested via web by Margie Rowe - Still no electrical permit pulled for electrical work
|
Final | 4/6/2018 | 4/6/2018 | 4/6/2018 | P | FAIL |
Chad Schwendiman
|
|
|
Inspection requested via web by Margie Rowe mini split installation ok need eletrical permit for eletrical portion before be able to final
|
Issue PAID IN FULL permit | | | 4/6/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/6/2018 | | DONE |
|
|
|
This permit was created on the web by Margie Rowe
|