First Notice | 11/30/2018 | 11/30/2018 | 7/27/2020 | | DONE |
Troy James
|
|
|
This permit finaled on the web by RM Mechanical
|
Final | 11/29/2018 | 11/30/2018 | 11/30/2018 | A | PASS |
Troy James
|
|
|
Gas Final Phone #: ###-#### Inspection requested via web by RM Mechanical
|
Pressure Test | 11/21/2018 | 11/21/2018 | 11/21/2018 | P | PASS |
Eric Strole
|
|
|
Gas Piping Rough In Phone #: ###-#### Inspection requested via web by RM Mechanical-60 lb gas test in penthouse pass.
|
Rough-in | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | FAIL |
Eric Strole
|
|
|
Gas Piping Rough In Phone #: ###-#### Inspection requested via web by RM Mechanical-Need to use a 100 lb gauge not a 200 lb gauge for a 60 lb test.
|
Rough-in | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by RM Mechanical- 100# test on hydronics fitness area and fire riser room nw corner pass- ok for pipe insulation- initialed contractor print
|
Pressure Test | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | PASS |
Troy James
|
|
|
Hydronic air pressure test level one Phone #: ###-#### Inspection requested via web by RM Mechanical 1st floor hydroncis test
|
Pressure Test | 8/9/2018 | 8/10/2018 | 8/10/2018 | A | PASS |
Troy James
|
|
|
Hydronic 2nd Floor Pressure Test Phone #: ###-#### Inspection requested via web by RM Mechanical 100# test
|
Pressure Test | 7/16/2018 | 7/17/2018 | 7/17/2018 | A | PASS |
Troy James
|
|
|
Hydronic Pressure Test on Main Phone #: ###-#### Inspection requested via web by RM Mechanical main from penthouse to first floor
|
Pressure Test | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Troy James
|
|
|
Hydronic pressure testing for insulating Hydronic Piping 3rd floor loop. Dennis White is the the Site Contact. Phone Number ###-####. Phone #: ###-#### Inspection requested via web by RM Mechanical Ok 100# test to 3rd floor hydronics, ok to insulate
|
Pressure Test | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | PART |
Troy James
|
|
|
Partial Pressure Test on Gas Piping. Contact: Dennis Phone #: ###-#### Inspection requested via web by RM Mechanical ok gas line from meter location to roof 68# test
|
Rough-in | 4/6/2018 | 4/9/2018 | 4/9/2018 | A | NR |
Eric Strole
|
|
|
Requesting partial rough-in.
Contact: Dennis White Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Issue PAID IN FULL permit | | | 4/6/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/6/2018 | | DONE |
|
|
|
This permit was created on the web by Melissa Kaae
|