Final | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PASS |
Jack Reynolds
|
|
|
please call half hour prio Phone #: ###-#### Inspection requested via web by thomas nguyen- air balance report with new exhaust fans was emailed and ok- final ok
|
Final | 6/26/2018 | 6/26/2018 | 6/26/2018 | P | PART |
Jack Reynolds
|
|
|
partial final with air balance report/ email stating when exhaust fans will be worked on and rebalanced/ extend flue on rtu up 3' above economizer - email of when new exhaust fans will be in place ok- air balance of exhaust systems at current state - EF 1 and EF 2 are below 80% and will need to be rebalanced for complete final- snorkel flue 3' above economizer ok
|
Final | 6/25/2018 | 6/26/2018 | 6/26/2018 | A | NR |
Jack Reynolds
|
|
|
please call half prio Phone #: ###-#### Inspection requested via web by thomas nguyen -scheduled a pm inspection- waiting on information and a fews things to be fixed by this afternoon
|
Final | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | NR |
Jack Reynolds
|
|
|
Thomas Phone #: ###-####- need to see air balance report on all nail stations for final
|
Rough-in | 6/18/2018 | 6/18/2018 | 6/18/2018 | P | PASS |
Jack Reynolds
|
|
|
ceiling ducting, please call 30 mins ahead - Tom Phone #: ###-####- ceiling tile cover ok- need balance dampers at each branch on exhaust for nail stations
|
Rough-in | 4/28/2018 | 4/30/2018 | 4/30/2018 | A | PART |
Jack Reynolds
|
|
|
please call half hour prio Phone #: ###-#### Inspection requested via web by thomas nguyen- Exhaust duct work above hard lid for nail stations and framing for access door R/I ok- still need to see bathroom exhaust fan mounted in ceiling before cover
|
Rough-in | 4/27/2018 | 4/27/2018 | 4/27/2018 | P | FAIL |
Jack Reynolds
|
|
|
please call half hour prio Phone #: ###-#### Inspection requested via web by thomas nguyen- seal all joints on nail station exhaust system above hard lid- also need access door framing in hard lid for eletric backdraft damper on south side for foot station
|
Rough-in | 4/24/2018 | 4/24/2018 | 4/24/2018 | P | PART |
Jack Reynolds
|
|
|
please call half hour prio Phone #: ###-#### Inspection requested via web by thomas nguyen- ductwork seal checked and ok for duct insulation
|
Conference | 4/13/2018 | 4/16/2018 | 4/16/2018 | A | DONE |
Chad Schwendiman
|
|
|
Please call ahead for access - Thomas Phone #: ###-#### - Discussed routing of duct work for the rtu in the back of the space, and insulation requirements
|
Application received | | | 4/13/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/13/2018 | | DONE |
|
|
|
|
First Notice | 7/11/2018 | 7/11/2018 | | | |
Jack Reynolds
|
|
|
|