Final | 8/24/2018 | 8/24/2018 | 8/24/2018 | A | PASS |
Jack Reynolds
|
|
|
IT room in airport final ok
|
Rough-in | 8/22/2018 | 8/24/2018 | 8/24/2018 | A | PASS |
Jack Reynolds
|
|
|
rough in - call mark Phone #: ###-#### Inspection requested via web by Brandon Sorensen- R/I ok
|
Rough-in | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | PART |
Chad Schwendiman
|
|
|
fire damper inspection Phone #: ###-#### Inspection requested via web by Brandon Sorensen - Framing for fire dampers okay, okay to insulate the DM ductwork
|
Issue PAID IN FULL permit | | | 5/10/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/10/2018 | | DONE |
|
|
|
This permit was created on the web by Brandon Sorensen
|
First Notice | 8/24/2018 | 8/24/2018 | | | |
Jack Reynolds
|
|
|
|