Final | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Ben Livingston
|
|
|
please let me know if you need a copy of the air balance report. if you provide an email, I will forward. Robin Phone #: ###-#### Inspection requested via web by Robin Cox
|
Final | 10/24/2018 | 10/25/2018 | 10/25/2018 | A | PART |
Ben Livingston
|
|
|
kitchen hood in managers apt damaged in shipment, waiting for replacement. Air Balance scheduled for 10/29/18. Robin cell ###-#### Phone #: ###-#### Inspection requested via web by Robin Cox all fire smoke damper access need to be labeled, condenser on roof needs more arma flex, regulator on roof needs freeze proof cap on vent, temp C.O. okay
|
Rough-in | 10/16/2018 | 10/17/2018 | 10/17/2018 | A | PASS |
Ben Livingston
|
|
|
duct seal first floor above grid ceiling Phone #: ###-#### Inspection requested via web by Robin Cox above grid 1st floor
|
Rough-in | 9/7/2018 | 9/10/2018 | 9/10/2018 | A | PASS |
Ben Livingston
|
|
|
reinspect first floor fire smoke Phone #: ###-#### Inspection requested via web by Robin Cox all firesmoke dampers on 1st floor okay, corridor ok
|
Rough-in | 9/6/2018 | 9/7/2018 | 9/7/2018 | A | FAIL |
Ben Livingston
|
|
|
first floor cover, garbage rooms 2-4 Phone #: ###-#### Inspection requested via web by Robin Cox 2-4 trash rooms ok 1st floor firesmoke dampers missing angles and drywall have gaps between angle and wall
|
Rough-in | 8/29/2018 | 8/29/2018 | 8/29/2018 | A | PASS |
Ben Livingston
|
|
|
cover for managers appartment Phone #: ###-#### Inspection requested via web by Robin Cox
|
Conference | 8/22/2018 | 8/23/2018 | 8/23/2018 | A | PASS |
Ben Livingston
|
|
|
cover for community room soffit, janitor 2-3;4. duct seal in Manager apartment Phone #: ###-#### Inspection requested via web by Robin Cox
|
Rough-in | 8/16/2018 | 8/16/2018 | 8/16/2018 | A | PASS |
Ben Livingston
|
|
|
cover for 2nd floor corridor and 1st floor rooms Phone #: ###-#### Inspection requested via web by Robin Cox 1st floor rooms and 2nd floor corridor
|
Rough-in | 8/13/2018 | 8/13/2018 | 8/13/2018 | A | PASS |
Ben Livingston
|
|
|
cover for 3rd floor corridor Phone #: ###-#### Inspection requested via web by Robin Cox 3rd floor corridor, firesmoke damper angle ok
|
Rough-in | 8/8/2018 | 8/9/2018 | 8/9/2018 | A | PASS |
Ben Livingston
|
|
|
Cover for 2nd floor rooms Phone #: ###-#### Inspection requested via web by Robin Cox 2nd floor rooms okay, all 1st floor firesmoke damper clearences
|
Rough-in | 8/6/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
Ben Livingston
|
|
|
4th floor corridor for cover Phone #: ###-#### Inspection requested via web by Robin Cox 4th floor corridor okay fire dampers okay
|
Rough-in | 7/30/2018 | 7/31/2018 | 7/31/2018 | A | PASS |
Ben Livingston
|
|
|
cover for 3rd floor and laundry rooms Phone #: ###-#### Inspection requested via web by Robin Cox all laundry rooms rough iin okay 3rd floor rooms okay 1st floor corridor ,office/lobbly duct seal okay 1st floor x15 firesmoke damper clearance okay
|
Rough-in | 7/16/2018 | 7/17/2018 | 7/17/2018 | A | PASS |
Ben Livingston
|
|
|
cover for rooms 401-406 Russ ###-#### Phone #: ###-#### Inspection requested via web by Robin Cox rooms 401-406 okay, tie in duct corridors 2nd and 3rd floor, part corridor duct seal 1st floor
|
Rough-in | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | PART |
Ben Livingston
|
|
|
Russ ###-#### Inspect duct in shaft Phone #: ###-#### Inspection requested via web by Robin Cox chase duct and fire smoke damper clearences 1st to 4th floor and angle inside chase okay 2nd and 3rd floor corridor part. seal , 4th floor corridor seal okay
|
Conference | 6/4/2018 | 6/5/2018 | 6/5/2018 | A | PASS |
Ben Livingston
|
|
|
please call with time to meet on site. Russ; ###-####, Calvin; ###-####
Robin ###-#### Phone #: ###-#### Inspection requested via web by Robin Cox
|
Conference | 5/22/2018 | 5/22/2018 | 5/22/2018 | P | PASS |
Ben Livingston
|
|
|
Russ is on site ###-#### Phone #: ###-#### Inspection requested via web by Robin Cox
|
Hold | | | 5/14/2018 | | DONE |
|
|
|
Left message to speak about fixture count on 41 unit m.f. (blh)
|
CHANGE STATUS TO (ISS) | | | 5/14/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/13/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/13/2018 | | DONE |
|
|
|
This permit was created on the web by Robin Cox
|
First Notice | 11/16/2018 | 11/16/2018 | | | |
Ben Livingston
|
|
|
|