Telephone call | | | 12/5/2018 | | DONE |
|
|
|
per email from Paige Mech. low voltage elec. DDC controls (done by Clima-Tech) included in final value given. Correct value without low voltage is $181,515.00
|
Print Statement | | | 12/3/2018 | | DONE |
|
|
|
|
Final | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- final ok- card signed
|
Rough-in | 7/24/2018 | 7/25/2018 | 7/25/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- seal on duct ok- onsulation and registers ok- ok for all ceiling tiles- need smoke detectors installed by final
|
Rough-in | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- still installing registers- ok for border tiles only- recall in when finished
|
Rough-in | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- R/I ok- seal on all duct ok- insulation on duct work now ok- ok for ceiling grid- will look at rest of insulation on grid inspection
|
Rough-in | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- south entry hard lid ok to cover- seal on duct ok- insulation ok most of building- reinspect when all complete
|
Rough-in | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | PART |
Brian Scoles
|
|
|
Cover. call in advance to showing up Phone #: ###-#### Inspection requested via web by Nicholas Paige- Insulation ok in vault, hard lid corridors and atm electrical room- ok for sheetrock cover
|
Rough-in | 6/8/2018 | 6/11/2018 | 6/11/2018 | A | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- seal on duct ok- ok to insulate ducts installed now- ok to sheetrock northwest room by bathroom only-
|
Rough-in | 5/23/2018 | 5/24/2018 | 5/24/2018 | A | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- seal on duct SW corner of building south of 45 degree wall ok for insulation- seal and insulation ok on duct above rear entry ok for cover only theses 2 places- recall in inspection when all seal on duct is complete
|
Issue PAID IN FULL permit | | | 5/23/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/22/2018 | | DONE |
|
|
|
This permit was created on the web by Nicholas Paige
|
Telephone call | | | 5/22/2018 | | DONE |
|
|
|
Nick Paige from Paige Mechanical Group called and needed the value to change. Changed value and added correct fee.
|
First Notice | 8/14/2018 | 8/14/2018 | | | |
Brian Scoles
|
|
|
|