First Notice | 4/2/2019 | 4/2/2019 | 2/3/2020 | | DONE |
Ben Livingston
|
|
|
This permit finaled on the web by Arcadio Martinez
|
Final | 4/1/2019 | 4/2/2019 | 4/2/2019 | A | PASS |
Ben Livingston
|
|
|
Phone #: ###-#### Inspection requested via web by Arcadio Martinez
|
Mec-Aging Inspection | 2/27/2019 | 2/27/2019 | 2/27/2019 | | CANC |
Ben Livingston
|
|
|
|
Pressure Test | 11/6/2018 | 11/7/2018 | 11/7/2018 | A | PASS |
Ben Livingston
|
|
|
Pressure test on 12 underground lines Phone #: ###-#### Inspection requested via web by Arcadio Martinez 20lb x12
|
Rough-in | 7/19/2018 | 7/20/2018 | 7/20/2018 | P | PASS |
Chad Schwendiman
|
|
|
Bldg. A Rough-In Phone #: ###-#### Inspection requested via web by Arcadio Martinez - Bldg A pass
|
Rough-in | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Ben Livingston
|
|
|
Phone #: ###-#### Inspection requested via web by Arcadio Martinez building B rough in
|
Rough-in | 6/26/2018 | 6/27/2018 | 6/27/2018 | P | FAIL |
Ben Livingston
|
|
|
Please contact our Project Manager Arcadio ###-#### to meet the inspector onsite. Phone #: ###-#### Inspection requested via web by Arcadio Martinez all fire dampers need to be in the sheet rock lid not above, gas flex cannot be strapped to wall studs condensate piping needs nail plates
|
Pressure Test | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Ben Livingston
|
|
|
Please contact our Project Manager Arcadio ###-#### to meet the inspector onsite. Phone #: ###-#### Inspection requested via web by Arcadio Martinez 20 lb gas x12 building B
|
Issue PAID IN FULL permit | | | 5/29/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/29/2018 | | DONE |
|
|
|
This permit was created on the web by Arcadio Martinez
|