Final | 8/22/2018 | 8/22/2018 | 8/22/2018 | P | PASS |
Jack Reynolds
|
|
|
Call jamon 20 min ahead Thanks Phone #: ###-#### Inspection requested via web by Manuel Canto- mini split ok- transfer airs ok- final ok
|
Rough-in | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | PASS |
Jack Reynolds
|
|
|
All is ready for inspector Phone #: ###-#### Inspection requested via web by Manuel Canto - transfer openings into new space ok
|
Rough-in | 6/7/2018 | 6/8/2018 | 6/8/2018 | A | PART |
Jack Reynolds
|
|
|
Call jamon 20 min ahead to meet inspector at jobsite Phone #: ###-#### Inspection requested via web by Manuel Canto- partial need return air or transfers into new space
|
Issue PAID IN FULL permit | | | 6/5/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/5/2018 | | DONE |
|
|
|
This permit was created on the web by Manuel Canto
|