Final | 9/28/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Krista Boss- final ok
|
Final | 9/26/2018 | 10/1/2018 | 9/27/2018 | A | CANC |
Brian Scoles
|
|
|
Phone #: ###-#### >> Inspection requested via web by Krista Boss Inspection cancelled from web by: Krista Boss
|
Rough-in | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Brian Scoles
|
|
|
Lay in grid. Aleks ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- R/A grills ok- ok for remaining cwiling tiles to be installed
|
Rough-in | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PASS |
Chad Schwendiman
|
|
|
lay in grid on RTU 1, 2, ; 3 Inspection requested via web by Krista Boss- final ok Phone #: ###-#### - Okay to cover grid ceilings except for around return grills. Ceiling tiles around return grills are to be left out for inspection once completed
|
Rough-in | 8/29/2018 | 8/31/2018 | 8/30/2018 | A | CANC |
Brian Scoles
|
|
|
lay in grid on RTU 1, 2, ; 3 Phone #: ###-#### Inspection requested via web by Krista Boss-
|
CHANGE STATUS TO (ISS) | | | 8/30/2018 | | DONE |
|
|
|
Some how final when passed on rough-in inspection. Per Brian
|
Rough-in | 8/13/2018 | 8/13/2018 | 8/13/2018 | P | PASS |
Brian Scoles
|
|
|
refrigeration Phone #: ###-#### Inspection requested via web by Krista Boss- R/I ok on refridgeration lines- ok for grid to be installed
|
Rough-in | 8/9/2018 | 8/9/2018 | 8/9/2018 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Krista Boss- R/I ok- will look at seal and hangers on final-ok for ceiling grid
|
Rough-in | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Krista Boss- need to fix all rips and tears in arma flex and support lineset for manager office- seal on duct south east corner needs sealed better off RTU 1- all ducting above grid needs insulated per M$ detail 6 and 7 excluding rooms under mezz- R/A drops di not match prints need to get engineers approval on whats installed- unit heater 1 needs installed per detal and length is pretty long? can not support to duct work- left correction notice with general and went over these issues
|
Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PART |
Chad Schwendiman
|
|
|
please call Aleks - part r/i on rtu 3 ;4 - ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss - Duct work okay for RTU's 3, and 4. Okay to cover ceilings and walls in back office area of building
|
Issue PAID IN FULL permit | | | 6/14/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 6/13/2018 | | |
|
|
|
|
Application received | | | 6/13/2018 | | DONE |
|
|
|
This permit was created on the web by Krista Boss
|
First Notice | 10/1/2018 | 10/1/2018 | | | |
Brian Scoles
|
|
|
|