Final | 10/10/2018 | 10/11/2018 | 10/11/2018 | A | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- duct blast and airbalance ok- final ok
|
Final | 10/8/2018 | 10/9/2018 | 10/9/2018 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- need duct blast and air balance report
|
Rough-in | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | PASS |
Jack Reynolds
|
|
|
PLZ LATE AM Phone #: ###-#### Inspection requested via web by Oleg Chervak- R/I ok
|
Pressure Test | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- 5lb flue pressure test ok- 20lb gas pressure test ok-
|
Rough-in | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- lineset needs insulation fixed- lineset needs nail plate half way down the wall
|
Pressure Test | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- 20lb gas pressure test fail gauge wouldnt zero out- 5lb flue test fail gauge was below 5lb
|
Issue PAID IN FULL permit | | | 6/27/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/27/2018 | | DONE |
|
|
|
This permit was created on the web by Oleg Chervak
|
Meeting | | | 6/27/2018 | | DONE |
|
|
|
sent email to oleg, alleyhvac@gmail.com, about incorrect sqft being seleteced, over paid for permit and how to request a refund. tried calling, but voice mailbox is not set up
|