First Notice | 4/2/2019 | 4/2/2019 | 4/2/2019 | | DONE |
Jack Reynolds
|
|
|
This permit finaled on the web by Amanda Farnsworth
|
DOC - Permit Finaled | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
Jack Reynolds
|
|
|
- final ok air balance ok
|
Final | 8/1/2018 | 8/2/2018 | 8/2/2018 | A | PART |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Amanda Farnsworth - R/I of 70 plus heat pump ok for ceiling cover- cooling tower ok- I also looked at all the piping for cooling tower and the insulation can continue being installed- need to see air balance reports on heat pumps for full final
|
Issue PAID IN FULL permit | | | 7/16/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/16/2018 | | DONE |
|
|
|
This permit was created on the web by Amanda Farnsworth
|