Print Statement | | | 4/13/2020 | | DONE |
|
|
|
3rd and final notice
|
Print Statement | | | 3/2/2020 | | DONE |
|
|
|
second statment
|
Print Statement | | | 2/5/2020 | | DONE |
|
|
|
|
Final | 9/26/2018 | 9/27/2018 | 9/27/2018 | A | PASS |
Brian Scoles
|
|
|
Everything is in ordee Phone #: ###-#### Inspection requested via web by Drew Tverdy- final ok- card signed
|
Final | 9/24/2018 | 9/24/2018 | 9/24/2018 | A | PART |
Brian Scoles
|
|
|
Hood system is balanced. Waiting on balance report so I can email. Hoping for a temperory final so his C of O can get signed off this afternoon. Phone #: ###-#### Inspection requested via web by Drew Tverdy- equipment set infinal place ok- need plywood installed in attic for access to roof- need curbs roofed in weather tight- need air balance report- temp occupancy ok- recall in final when all items are completed
|
Rough-in | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PASS |
Brian Scoles
|
|
|
Second layer of fire wrap and roof top inpsector. We will be there by 2:30 finishing up some other things. Phone #: ###-#### Inspection requested via web by Drew Tverdy- second layer wrap ok on grease duct and smoker- roof ok- need to roof in curbs weater tight by final- need to install plywood in attic where ladder from serving area is- talked to owner about this- need equipment set into working place by final inspection and have air balance report onsite
|
Rough-in | 9/12/2018 | 9/12/2018 | 9/12/2018 | A | PASS |
Brian Scoles
|
|
|
We will be ready by 10:00 Phone #: ###-#### Inspection requested via web by Drew Tverdy- light test pass on smoker- ok fir fire wrap
|
Rough-in | 8/22/2018 | 8/22/2018 | 8/22/2018 | P | PASS |
Brian Scoles
|
|
|
light test- light tes pass x 2 above ceiling- zero clearance hood installed
|
Rough-in | 8/22/2018 | 8/22/2018 | 8/22/2018 | A | PASS |
Brian Scoles
|
|
|
Light test in hiid connection. Will be ready at 11:00 Phone #: ###-#### Inspection requested via web by Drew Tverdy- light test both connections to hood ok- MAU main duct seal ok-
|
Rough-in | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Brian Scoles
|
|
|
Light test on grease duct. Will be ready by 1:00 Phone #: ###-#### Inspection requested via web by Drew Tverdy- light test pass on 1- 8' piece 14x24- 1- 2' a4x24 to 14x15 transition- 1 14x15 90 degree and 32" of 14x15- need to add smoker to permit and update valuation and pay fee before next inspection
|
Rough-in | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | CANC |
Brian Scoles
|
|
|
Light test on grease duct. Phone #: ###-#### >> Inspection requested via web by Drew Tverdy Inspection cancelled from web by: Drew Tverdy
|
Issue PAID IN FULL permit | | | 7/17/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 7/17/2018 | | |
|
|
|
|
Application received | | | 7/17/2018 | | DONE |
|
|
|
This permit was created on the web by Drew Tverdy
|
First Notice | 9/27/2018 | 9/27/2018 | | | |
Brian Scoles
|
|
|
|