First Notice | 4/8/2019 | 4/8/2019 | 7/27/2020 | | DONE |
Troy James
|
|
|
This permit finaled on the web by RM Mechanical
|
Mec-Aging Inspection | 4/8/2019 | 4/8/2019 | 4/8/2019 | | PASS |
Troy James
|
|
|
|
DOC - Permit Finaled | 4/8/2019 | 4/8/2019 | 4/8/2019 | A | PASS |
Troy James
|
|
|
|
Final | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Troy James
|
|
|
|
Final | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | FAIL |
Troy James
|
|
|
Phone #: ###-#### Inspection requested via web by RM Mechanical Need air balance report
|
Rough-in | 9/24/2018 | 9/24/2018 | 9/24/2018 | A | PASS |
Troy James
|
|
|
Ok grease duct in shaft area. Received letter from captive aire to delete cleanouts at vertical ducts in shaft area. Due to ducts being inaccessable.
|
Rough-in | 9/18/2018 | 9/20/2018 | 9/20/2018 | A | FAIL |
Troy James
|
|
|
Grease Duct Rough In Phone #: ###-#### Inspection requested via web by RM Mechanical Need letter from captive air stating why clean out is not required every 20' per IMC.
|
Rough-in | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | PART |
Troy James
|
|
|
Cover inspection. Contact: Mark Hammer Phone #: ###-#### Inspection requested via web by RM Mechanical ok to insulate duct at make up Need clean out at fire damper Contractor to verify why captive air shows no clean out on there duct layout. Clean out required every 20'
|
Issue PAID IN FULL permit | | | 7/25/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/25/2018 | | DONE |
|
|
|
This permit was created on the web by RM Mechanical
|