Final | 10/24/2018 | 10/25/2018 | 10/25/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Robin Cox- final ok- card signed
|
Rough-in | 9/28/2018 | 10/1/2018 | 10/1/2018 | A | PASS |
Brian Scoles
|
|
|
for cover Phone #: ###-#### Inspection requested via web by Robin Cox- R/I ok- ok for ceiling tiles- flex to registers and insulation ok
|
Rough-in | 9/20/2018 | 9/21/2018 | 9/21/2018 | P | PASS |
Brian Scoles
|
|
|
duct sealing Phone #: ###-#### Inspection requested via web by Robin Cox- seal on remaining ducts- ok to insulate and install ceiling grid- recall in when registers are installed
|
Rough-in | 8/31/2018 | 9/4/2018 | 9/4/2018 | A | PASS |
Brian Scoles
|
|
|
duct seal 3rd floor Phone #: ###-#### Inspection requested via web by Robin Cox- seal on duct ok- ok to insulate- missing fan coil units- recall in inspection when grids installed-
|
Rough-in | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Brian Scoles
|
|
|
cover for bathrooms Phone #: ###-#### Inspection requested via web by Robin Cox- seal on duct above bath rooms ok- need to insulate 10' of supply duct above bathroom hard lid- ok for cover- recall in inspection when rest of install is complete and sealed
|
Issue PAID IN FULL permit | | | 8/18/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/18/2018 | | DONE |
|
|
|
This permit was created on the web by Robin Cox
|
First Notice | 10/25/2018 | 10/25/2018 | | | |
Brian Scoles
|
|
|
|