First Notice | 12/21/2018 | 12/21/2018 | 1/28/2019 | | DONE |
Brian Scoles
|
|
|
This permit finaled on the web by Dan Flaherty
|
Final | 12/21/2018 | 12/21/2018 | 12/21/2018 | P | PASS |
Brian Scoles
|
|
|
Jake is your contact Phone #: ###-#### Inspection requested via web by Kim Adams- final ok- card signed
|
Final | 12/19/2018 | 12/20/2018 | 12/20/2018 | A | PART |
Brian Scoles
|
|
|
Jake will be your contact Phone #: ###-#### Inspection requested via web by Kim Adams- still need label on fire/smoke dampers in gym- Rest is good- will need other mechanical contractor inspection done to final out- temp occvupancy ok
|
Final | 12/17/2018 | 12/18/2018 | 12/18/2018 | A | PART |
Brian Scoles
|
|
|
Jake is your contact Phone #: ###-#### Inspection requested via web by Kim Adams- need to insulate R/A square to rounds in both classrooms- need uv protection on lineset on roof- need to label all fire/smoke dampers- need to fix gap in fire/smoke damper angle in hallway to much gap- flex connector shields need installed on roof to protect from sun- air balance report ok- recall in when corrections are made
|
Rough-in | 11/29/2018 | 11/30/2018 | 11/30/2018 | A | PASS |
Brian Scoles
|
|
|
inspection for ceiling cover . Jake is your contact Phone #: ###-#### Inspection requested via web by Kim Adams- R/I ok all building- registers flex and insulation all good in classrooms and corridirs- ok for ceiling tiles- call in final when ready
|
Rough-in | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Brian Scoles
|
|
|
Rough in for the Gym. Robert Will be your contact. Phone #: ###-#### Inspection requested via web by Kim Adams- gym duct ok- fire smoke damper angles all building ok- rtus on roof ok- missi ng some seal for weather tight- ok for ceiling grid
|
Rough-in | 11/2/2018 | 11/5/2018 | 11/5/2018 | A | PART |
Brian Scoles
|
|
|
approval for duct wrap on rtu 3. Jake is your contact. Phone #: ###-#### Inspection requested via web by Kim Adams- seal on RTU 3 duct work ok- ok to insulate
|
Rough-in | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | PART |
Brian Scoles
|
|
|
approval for cover on the bathroom ceilings. Jake is your contact Phone #: ###-#### Inspection requested via web by Kim Adams- insulation in 2 bathrooms ok- ok for sheetrock bathrooms only
|
Rough-in | 10/23/2018 | 10/24/2018 | 10/24/2018 | A | PASS |
Brian Scoles
|
|
|
fire damper inspection - contact is Jake Phone #: ###-#### Inspection requested via web by Kim Adams- 2 fire dampers clearances framing ok southwest room
|
Rough-in | 10/19/2018 | 10/22/2018 | 10/22/2018 | A | PART |
Brian Scoles
|
|
|
approval for duct wrap. Jake is your contact. Phone #: ###-#### Inspection requested via web by Kim Adams- seal on duct southside of corridor ok to insulate- corridor dampers framing ok- ok for sheet rock
|
Issue PAID IN FULL permit | | | 8/23/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/23/2018 | | DONE |
|
|
|
This permit was created on the web by Kim Adams
|