Conference | 11/9/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Brian Scoles
|
|
|
Need inspection for approval of placement of mantel above fireplace. All finish work completed. Thank you very much. Phone is ###-#### Phone #: ###-#### Inspection requested via web by James Kappel
|
Final | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Brian Scoles
|
|
|
Need inspection for approval of placement of mantel above fireplace. All finish work completed. Thank you very much. Phone is ###-#### Phone #: ###-#### Inspection requested via web by James Kappel- fireplace ok- mantel ok
|
Conference | 10/18/2018 | 10/19/2018 | 10/19/2018 | A | DONE |
Troy James
|
|
|
Follow-up to check. Framing completed for wood burning fireplace. Also installed fire barrier caulking between ceiling fire spacer and chimney pipe. Anytime in morning works. Phone #: ###-#### Inspection requested via web by James Kappel
|
Rough-in | 10/19/2018 | 10/19/2018 | 10/19/2018 | A | PASS |
Troy James
|
|
|
Follow-up to check. Framing completed for wood burning fireplace. Also installed fire barrier caulking between ceiling fire spacer and chimney pipe. Anytime in morning works. Phone #: ###-#### Inspection requested via web by James Kappel
|
Conference | 10/13/2018 | 10/15/2018 | 10/15/2018 | A | DONE |
Brian Scoles
|
|
|
Fireplace set in position, double wall chimney installation completed. Would like to have clearances checked before closing up. Any time in a.m. works. Thank you very much. Phone #: ###-#### Inspection requested via web by James Kappel- clearances on pipe ok- insulation shield ok- discussed framing- recall in R/I inspection when framing complete
|
Issue PAID IN FULL permit | | | 9/4/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/4/2018 | | DONE |
|
|
|
This permit was created on the web by James Kappel
|