Final | 2/13/2019 | 2/14/2019 | 2/14/2019 | A | PASS |
Jack Reynolds
|
|
|
Joe Phone #: ###-#### - final ok - couldnt find card onsite to sign
|
Final | 2/12/2019 | 2/12/2019 | 2/12/2019 | P | FAIL |
Jack Reynolds
|
|
|
Joe Phone #: ###-#### - no access to job site - jobsite was fenced off and locked could find anyone to let me
|
Final | 12/19/2018 | 12/19/2018 | 12/19/2018 | P | PART |
Jack Reynolds
|
|
|
Joe Phone #: ###-#### - still need to see c02 sensors installed and interlocked with exhausts and make up air dampers
|
Pressure Test | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Jack Reynolds
|
|
|
Joe Phone #: ###-#### - 60lb gas pressure test- the R/I is still only a partial need to check unit heaters and hvac equipment
|
Rough-in | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | PART |
Troy James
|
|
|
Partial TI, Rough-in & P/T - Joe Phone #: ###-#### ok to cover offices and restroom area. No gas inspection or warehouse.
|
Issue PAID IN FULL permit | | | 10/1/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/1/2018 | | DONE |
|
|
|
This permit was created on the web by Joe Taylor
|
First Notice | 2/14/2019 | 2/14/2019 | | | |
Jack Reynolds
|
|
|
|