First Notice | 4/15/2019 | 4/15/2019 | 4/24/2019 | | DONE |
Brian Scoles
|
|
|
This permit finaled on the web by Stacia Haumann
|
Final | 4/12/2019 | 4/15/2019 | 4/15/2019 | A | PASS |
Brian Scoles
|
|
|
if questions call Jerry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann- final on gas piping ok
|
Pressure Test | 3/22/2019 | 3/25/2019 | 3/25/2019 | A | PASS |
Brian Scoles
|
|
|
If questions call Jerry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann- 60lb gas test outside above ground to inside building pass- underground done by different contractor they will need to pull permit and test underground piping- hydronic test pass
|
Issue PAID IN FULL permit | | | 11/6/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/6/2018 | | DONE |
|
|
|
This permit was created on the web by Stacia Haumann
|