Final | 7/18/2019 | 7/19/2019 | 7/19/2019 | A | PASS |
Brian Scoles
|
|
|
Mechanical Gas fireplace Final inspection Please call Jon @ ###-#### when headed that way. Phone #: ###-#### Inspection requested via web by Dan Otero- gas fireplace ok- wood stove in basement ok, removing mantel and not installing one per conversation with general contractor stone on wall to ceiling
|
Final | 7/10/2019 | 7/10/2019 | 7/10/2019 | P | FAIL |
Brian Scoles
|
|
|
Mechanical Gas fireplace final inspection Manual in kitchen drawer Please call Jon @ ###-#### when headed that way. Phone #: ###-#### Inspection requested via web by Dan Otero- gas fireplace ok- wood stove downstairs needs combustible mantel installed per manufacture installation instructions height to low
|
Final | 7/3/2019 | 7/3/2019 | 7/3/2019 | P | FAIL |
Brian Scoles
|
|
|
Mechanical Gas fireplace final inspection Please call Jon @ ###-#### when headed that way. Phone #: ###-#### Inspection requested via web by Dan Otero- need installation instruction for wood fireplace downstairs onsite none could be found did find ones for gas fireplace- called number listed no answer
|
Rough-in | 1/25/2019 | 1/28/2019 | 1/28/2019 | A | PASS |
Brian Scoles
|
|
|
1 gas fireplace 1 wood stove R/I ok
|
Rough-in | 1/25/2019 | 1/25/2019 | 1/25/2019 | P | PART |
Brian Scoles
|
|
|
framing needs complete- builder will have ready monday- i rescheduled for AM inspection
|
Rough-in | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Dan Otero- R/I basement and first floor ok to cover talked with builder onsite- crew there finishing 2nd floor- i will schedule afternoon inspection today and look at 2nd floor
|
Rough-in | 1/16/2019 | 1/16/2019 | 1/16/2019 | P | PART |
Brian Scoles
|
|
|
Partial inspection. We were not able to penetrate the roof for safety reasons. We will be back to finish when roof is not slick. Phone #: ###-#### Inspection requested via web by Dan Otero- framing needs completed- 4" and 6" pipes need to be seucured/strapped in chase- need to finish roof penetrations- need to finish fire caulking- flue needs clearance to combustibles second floor chase and supported- all piping needs supported to manufactures ionstallation instructions- ok to cover rest of house excluding 2nd floor attic space and chases on all levels around fireplace- talked with building inspector about this he is aware
|
Rough-in | 1/15/2019 | 1/15/2019 | 1/15/2019 | P | CANC |
Brian Scoles
|
|
|
Phone #: ###-#### >> Inspection requested via web by Dan Otero Inspection cancelled from web by: Dan Otero
|
Rough-in | 12/19/2018 | 12/20/2018 | 12/20/2018 | A | PART |
Brian Scoles
|
|
|
We would appreciate a partial inspection to inspect the gas fireplace. The wood/ pellet stove will be roughed in at a later date. Thank you. Phone #: ###-#### Inspection requested via web by Dan Otero- Gas fireplace R/I ok- contractor waiting on decision on wood/pellet stove per conversation with Dan- will call in inspection when installed- do not cover mechanical sticker left onsite ttil this is completed
|
Issue PAID IN FULL permit | | | 12/18/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/18/2018 | | DONE |
|
|
|
This permit was created on the web by Dan Otero
|