Final | 2/11/2019 | 2/11/2019 | 2/11/2019 | P | PASS |
Jack Reynolds
|
|
|
Please call ahead for access Phone #: ###-#### Inspection requested via web by Matthew BLANKENSHIP - final ok signed card for occ
|
Final | 1/2/2019 | 1/3/2019 | 1/3/2019 | A | CANC |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Matthew BLANKENSHIP - needed to be a R/I inspection
|
Rough-in | 1/3/2019 | 1/3/2019 | 1/3/2019 | A | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Matthew BLANKENSHIP - R/I of inline fans for game rooms and transfer air ok - schedule final when trim is finished
|
Issue PAID IN FULL permit | | | 1/2/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 12/30/2018 | | |
|
|
|
|
Application received | | | 12/30/2018 | | DONE |
|
|
|
This permit was created on the web by Matthew BLANKENSHIP
|
First Notice | 2/11/2019 | 2/11/2019 | | | |
Jack Reynolds
|
|
|
|