Final | 2/4/2019 | 2/5/2019 | 2/5/2019 | P | PASS |
Jack Reynolds
|
|
|
Inspection requested via web by Konrad Swartz - final ok
|
Final | 2/4/2019 | 2/5/2019 | 2/4/2019 | A | CANC |
Jack Reynolds
|
|
|
>> Inspection requested via web by Konrad Swartz Inspection cancelled from web by: Konrad Swartz
|
Final | 2/1/2019 | 2/4/2019 | 2/4/2019 | A | PART |
Jack Reynolds
|
|
|
Inspection requested via web by Konrad Swartz - upstairs units had access- need to finish filling out duct blast stickers upstairs- still need access to units downstairs- dyrer vent done by other needs finished
|
Conference | 1/31/2019 | 2/1/2019 | 2/1/2019 | A | PASS |
Jack Reynolds
|
|
|
Duct Blast 9:30 Shane ###-#### Inspection requested via web by Konrad Swartz - all units duct blast ok
|
Rough-in | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | PASS |
Jack Reynolds
|
|
|
Rough in and Duct Blast 9:30 Inspection requested via web by Konrad Swartz - R/I ok -unit 103 duct blast ok - air balance will be ready to check for final
|
Rough-in | 1/23/2019 | 1/23/2019 | 1/23/2019 | P | PART |
Jack Reynolds
|
|
|
Inspection requested via web by Konrad Swartz - Man J needs to be stamped by the city and onsite - range hood vent needs to be smooth walled pipe - one dryer vent needs new back draft damper installed - one unit has line set insulation that needs fixed
|
Review - MECHANICAL | 1/18/2019 | 1/18/2019 | 1/18/2019 | | PASS |
Troy James
|
|
|
|
Final | 1/14/2019 | 1/16/2019 | 1/16/2019 | A | CANC |
Jack Reynolds
|
|
|
The Builder and Property Manager are requesting 8:30 to 10:30 AM as these are occupied >> Inspection requested via web by Konrad Swartz Inspection cancelled from web by: Konrad Swartz
|
Final | 1/8/2019 | 1/9/2019 | 1/9/2019 | P | FAIL |
Jack Reynolds
|
|
|
Property manager is requesting 3pm he will be onsite Inspection requested via web by Konrad Swartz - need man J stamped and approved onsite - need to add bathroom exhaust fan and duct work to permit - lineset need UV protection - condensate line need extended down to the ground from the 2nd floor
|
Issue PAID IN FULL permit | | | 1/4/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 1/4/2019 | | DONE |
|
|
|
This permit was created on the web by Konrad Swartz
|
Miscellaneous action | | | 1/4/2019 | | DONE |
|
|
|
per C_P ok to pull 1 permit for the multy-family but needs to include all 4 units when calling in inspections
|
First Notice | 2/5/2019 | 2/5/2019 | | | |
Jack Reynolds
|
|
|
|