Permit Information
Permit NumberMEC19-00438
StatusFinaled
Name WESTERN HEATING & A/C
Site Address 6615 S FEDERAL WAY
Project NamePeterbilt Paint Booth
Customer Number 
ePlanReviewNo
Description
Alteration: INSTALL 2 TUBE HEATERS AND EXHAUST AND MAKE UP AIR//Paint Booth (forgot to add when creating permit, value is the same) j.a.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final4/17/20194/18/20194/18/2019APASS
DetailsJack Reynolds
questions, please call Zac ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
- received email from engineer on louver AFF ok
- also received email on operation of equipment
- final ok
-couldnt find card to sign onsite
Card not on site to sign4/18/20194/18/20194/18/2019PPASS
DetailsJack Reynolds
questions, please call Zac ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
CHANGE STATUS TO (ISS)  4/17/2019 DONE
still need to pass final inspection
Final3/20/20193/20/20193/20/2019PFAIL
DetailsJack Reynolds
ANY QUESTIONS, PLEASE CALL ZAC ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt

- side wall exhaust and make up needs to be 12' AFF like the print shows.
- Exhaust and make up air needs to be functional and it looks like the electrical contractor is working on this
Final3/19/20193/19/20193/19/2019PNR
DetailsJack Reynolds
questions you can call Zac Barnes ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
- unit heaters ok
- need to see exhaust and make up air finished before final
- need to add description on permit the work being done on exhaust and make up air outside the paint booth
- talked with Kay from ultimate steel and paint booth is being done by another contractor. I told kay that the paint booth exhaust and makeup air ducting needs to have a mechanical permit pulled
Final2/19/20192/20/20192/20/2019PCANC
DetailsJack Reynolds
INSTALLER BRANDAN ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
Rough-in2/20/20192/20/20192/20/2019PPART
DetailsJack Reynolds
INSTALLER BRANDAN ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
- unit heater flues need seams sealed per manufactures specs
- also need to check with engineer about unit heater to the north and its termination point out the buidling being moved to the east wall. Prints show the termination point on the north wall
- gas line is a high pressure system and each unit heater needs its regs and sediment traps/pressure ports installed. other contractor performed gas line for new building
Issue PAID IN FULL permit  1/30/2019 DONE
Payment received via Govolutions
Application received  1/30/2019 DONE
This permit was created on the web by Aaron Alandt
First Notice4/18/20194/18/2019   
DetailsJack Reynolds
First Notice3/20/20193/20/2019   
DetailsJack Reynolds