Final | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by fred lopez- final ok- signed card
|
Final | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by fred lopez- need drip leg on gas line- need to extend flue 3 feet above economizer within 10 feet- need to label gas line at meter for suite address- recall in when ready
|
Rough-in | 3/19/2019 | 3/20/2019 | 3/20/2019 | A | PASS |
Chad Schwendiman
|
|
|
grid inspection duct insulate Phone #: ###-#### Inspection requested via web by fred lopez - Okay to cover ceiling
|
Rough-in | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | PART |
Brian Scoles
|
|
|
ceiling grid inspection Phone #: ###-#### Inspection requested via web by fred lopez- seal on duct ok- ok to insulate
|
Issue PAID IN FULL permit | | | 2/22/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 2/22/2019 | | |
|
|
|
|
Application received | | | 2/22/2019 | | DONE |
|
|
|
This permit was created on the web by fred lopez
|
First Notice | 3/21/2019 | 3/21/2019 | | | |
Brian Scoles
|
|
|
|