Final | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | PASS |
Brian Scoles
|
|
|
Mechanical Final inspection needed for Am please contact Karl with any questions ###-#### thank you Phone #: ###-#### Inspection requested via web by Karl Hestekin- final ok- card signed
|
Rough-in | 3/1/2019 | 3/1/2019 | 3/1/2019 | P | PASS |
Brian Scoles
|
|
|
Rough-in needed for Tutoring Center if you have questions contact Dave at ###-#### or Karl at ###-#### thanks Phone #: ###-#### Inspection requested via web by Karl Hestekin- need to seal wye branch to toilet and storage room-seal ok on rest- ok to insulate
|
Issue PAID IN FULL permit | | | 3/1/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/1/2019 | | DONE |
|
|
|
This permit was created on the web by Karl Hestekin
|
First Notice | 4/11/2019 | 4/11/2019 | | | |
Brian Scoles
|
|
|
|