Information based on query as of Monday, July 22, 2024.
Permit Information
Permit NumberMEC19-01273
StatusFinaled
Name ALPINE GAS FIREPLACES
Site Address 880 W RIVER ST
Project Name 
Customer Number 
ePlanReviewNo
Description
13 fireplaces for the dwellings at the Afton apartments-units 207, 206, 212, 307, 306, 312, 407, 406, 412, 507, 512 & 508
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled10/7/201910/7/201910/7/2019APASS
DetailsChad Schwendiman
Unit 506 is permited on it's own permit
Telephone call  10/2/2019 DONE
Brandy with Alpine Fireplaces called to remove 506 from this permit as she is adding a new MEC permit to BLD19-03312, which is specific to unit 506
Final9/13/20199/19/20199/18/2019APART
DetailsChad Schwendiman
PLEASE CALL JESSE ###-#### - PRIOR TO ARRIVAL
need final inspections on all remaining units, excluding 506
Thank you,
Mike
Phone #: ###-#### Inspection requested via web by Mike Almanza - Temporary occupancy okay except for 506
Final9/13/20199/19/20199/13/2019ACANC
DetailsChad Schwendiman
PLEASE CALL JESSE PRIOR TO ARRIVAL ###-####
NEED FINAL INSPECTIONS ON ALL REMAINING UNITS, INCLUDING UNIT 506 Phone #: ###-#### >> Inspection requested via web by Mike Almanza Inspection cancelled from web by: Mike Almanza
Final9/5/20199/6/20199/6/2019APART
DetailsBen Livingston
JESSE ###-####
UNITS ON 2ND FLOOR ONLY Phone #: ###-#### Inspection requested via web by Mike Almanza
- 2nd floor fireplaces -
Rough-in8/9/20198/9/20198/9/2019PPASS
DetailsChad Schwendiman
request re-inspection at unit 506. Call Project super (Jesse) ahead of time for access: Jesse ###-####. Flexible ducting was changed to rigid pipe. Phone #: ###-#### Inspection requested via web by Mike Almanza
Rough-in8/8/20198/8/20198/8/2019PFAIL
DetailsChad Schwendiman
JESSE ###-#### UNIT 506 FIREPLACE ONLY, PIPE HAS ALREADY BEEN INSPECTED.
ANY QUESTIONS, CALL ALPINE MANAGER MIKE ALMANZA ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza - Need 1" clearance between vent pipe and flexible ducting
Rough-in8/8/20198/8/20198/8/2019PCANC
DetailsChad Schwendiman
JESSE ###-####
UNIT 500 ONLY - PIPE WAS ALREADY INSPECTED.
QUESTIONS? CALL ALPINE MANAGER MIKE ALMANZA ###-#### Phone #: ###-#### >> Inspection requested via web by Mike Almanza Inspection cancelled from web by: Mike Almanza
Rough-in7/22/20197/23/20197/23/2019APASS
DetailsChad Schwendiman
unit 506; Must call ahead to meet Jesse. You will be able to view the pipe from the roof. Flashing is elevated to view clearances have been maintained. Jesse can get you on the roof to show you where the vent is located.
PLEASE CALL JESSE ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza - Vent pipe through attic to roof okay. Recall once fireplace is installed
Rough-in7/22/20197/22/20197/22/2019PFAIL
DetailsChad Schwendiman
unit 506
Jesse ###-####
MIKE ALMANZA ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza - Still need to see vent in attic
Rough-in7/17/20197/18/20197/18/2019AFAIL
DetailsChad Schwendiman
Requesting a partial, rough-in, inspection for unit 506 only.

Note: venting runs through a fire stop, and a full height attic radiation shield to the roof “lid”. Fireplace framing and fireplace will be installed next week. Fireplace install manual is tacked to the drywall where the fireplace will be located in the living room.
Job site contact: Jesse ###-####

Photo’s available upon request.
Phone #: ###-#### Inspection requested via web by Mike Almanza - Need to be able to see clearance around vent pipe in attic space
Rough-in6/17/20196/18/20196/18/2019APASS
DetailsChad Schwendiman
JASON ###-####
unit 406 ready for rough inspection Phone #: ###-#### Inspection requested via web by Mike Almanza
Rough-in6/3/20196/3/20196/3/2019PFAIL
DetailsBen Livingston
SUPER: JASON
UNITS 406, 407, 412, 417, 507, 512
all gas shut off valves need access doors - DOORS ARE PRESENT
fireplace in unit 406 gas piping doesnt enter cabinet - FOR HVAC TO ADDRESS
flue piping has to much horizontal - POWER VENTED, PLEASE SEE MANUAL
PLEASE CALL MIKE WITH ANY QUESTIONS ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza
-fireplace 507okay
-still reed rough-in framing for access doors
-still need gas piping to ener the cabinet on 406,this work needs to be complete before i can pass the rough-in power vent is acceptable
Rough-in5/31/20195/31/20195/31/2019PFAIL
DetailsBen Livingston
UNITS 406, 407, 412, 417, 506, 507, 512, 517 Phone #: ###-#### Inspection requested via web by Mike Almanza
all gas shut off valves need access doors, no fireplace in unit 506, there is no unit 517,
fireplace in unit 406 gas piping doesnt enter cabinet, flue piping has to much horizontal
Rough-in5/31/20195/31/20195/31/2019PCANC
DetailsChad Schwendiman
UNITS: 406, 407, 412, 417, 506, 507, 512 Phone #: ###-#### >> Inspection requested via web by Mike Almanza Inspection cancelled from web by: Mike Almanza
Rough-in5/31/20195/31/20195/31/2019PCANC
DetailsChad Schwendiman
UNITS 512, 507, 406 Phone #: ###-#### >> Inspection requested via web by Mike Almanza Inspection cancelled from web by: Mike Almanza
Rough-in4/3/20194/3/20194/3/2019PPASS
DetailsChad Schwendiman
reinspection request for units 206 and 207 this afternoon. Any questions, please call Mike at ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza
Rough-in4/1/20194/1/20194/1/2019PPART
DetailsChad Schwendiman
Units:
206
207
306
307
312
Phone #: ###-#### Inspection requested via web by Mike Almanza - Units 207, 307, and 312 okay to cover. Units 206, and 207 need 2" clearance to combustables above horizontal vent pipe
Rough-in3/29/20194/1/20194/1/2019APASS
DetailsChad Schwendiman
Mike ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza - Unit 212 okay
Rough-in3/28/20193/29/20193/29/2019PFAIL
DetailsChad Schwendiman
UNIT 212 ONLY
MIKE ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza - Need installation instructions left on site for fireplace
Issue PAID IN FULL permit  3/28/2019 DONE
Payment received via Govolutions
Application received  3/28/2019 DONE
This permit was created on the web by Mike Almanza
First Notice10/7/201910/7/2019   
DetailsChad Schwendiman