Final | 6/13/2019 | 6/14/2019 | 6/14/2019 | P | PASS |
Jack Reynolds
|
|
|
Inspection failed pending an Air Balance report. The report has been emailed to Jack Reynolds. Please pass. Phone #: ###-#### Inspection requested via web by Arielle Hendricks - final ok
|
Final | 5/31/2019 | 6/6/2019 | 6/6/2019 | P | FAIL |
Jack Reynolds
|
|
|
This customer needs as late in the PM as possible for her inspection. Please call on way: Hannah ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks - duct blast ok - need to see air balance report
|
Pressure Test | 5/21/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Arielle Hendricks - 20lb gas pressure test ok - tagged meter location - will need to see air balance report and duct blast test for final
|
Pressure Test | 5/21/2019 | 5/22/2019 | 5/21/2019 | A | CANC |
Jack Reynolds
|
|
|
Phone #: ###-#### >> Inspection requested via web by Arielle Hendricks Inspection cancelled from web by: Arielle Hendricks
|
Review - MECHANICAL | 5/21/2019 | 5/21/2019 | 5/21/2019 | | DONE |
Troy James
|
|
|
Manual j report heating only system
|
Issue PAID IN FULL permit | | | 5/17/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/17/2019 | | DONE |
|
|
|
This permit was created on the web by Arielle Hendricks
|