Final | 10/16/2019 | 10/17/2019 | 10/17/2019 | A | PASS |
Jack Reynolds
|
|
|
Fernado Phone #: ###-#### - final ok
|
Final | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | FAIL |
Jack Reynolds
|
|
|
Fernado Phone #: ###-#### - A/C needs locking caps installed on service ports - supply run into laundry room needs installed - air balance needs finished contractor is working on it
|
Rough-in | 7/5/2019 | 7/5/2019 | 7/5/2019 | P | PASS |
Jack Reynolds
|
|
|
Fernado Phone #: ###-#### - R/I and 5lb flue pressure test ok - another mec permit for the gas line hasn't passed R/I yet
|
Rough-in | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | FAIL |
Jack Reynolds
|
|
|
Fernando Phone #: ###-#### - Man J needs approved by the City of Boise - duct work needs to match the Man J - gas line needs to be extended to mec room - one exhaust fan needs connected - supply boots need sealed - one branch line needs sealed under stairs - need to see fresh air installed on system - line set needs installed for R/I
|
Application received | | | 6/27/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/27/2019 | | DONE |
|
|
|
|