First Notice | 1/28/2020 | 1/28/2020 | 3/19/2020 | | DONE |
Jack Reynolds
|
|
|
This permit finaled on the web by Kathy Youngkin
|
Final | 1/28/2020 | 1/28/2020 | 1/28/2020 | P | PASS |
Jack Reynolds
|
|
|
Mech. final for project. call Adrian ###-#### 30 mins out to meet inspector. Phone #: ###-#### Inspection requested via web by adrian manzo - final ok - occ card signed
|
Pressure Test | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | PASS |
Jack Reynolds
|
|
|
Adrian Phone #: ###-#### - 2 60lb gas pressure tests one to new water heater and one to kitcken ok - still need to see updated and stamped prints onsite -performed gas pressure tests to get heat back to building
|
Conference | 12/12/2019 | 12/12/2019 | 12/12/2019 | P | DONE |
Jack Reynolds
|
|
|
CFM exhaust in kitchen Phone #: ###-#### Inspection requested via web by adrian manzo -two small range hoods will be installed in kitcken - type ll hood will be installed over dishwasher per prints
|
Conference | 12/11/2019 | 12/12/2019 | 12/12/2019 | A | CANC |
Jack Reynolds
|
|
|
Conference for kitchen CFM Exhaust. Job 42115. Contact is Adrian ###-#### Phone #: ###-#### Inspection requested via web by Kathy Youngkin
|
Pressure Test | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | FAIL |
Jack Reynolds
|
|
|
Pressure test on gas above laundry room for water heater. call 30 mins before arriving. Phone #: ###-#### Inspection requested via web by adrian manzo - need stamped set of prints onsite
|
Rough-in | 8/15/2019 | 8/16/2019 | 8/16/2019 | A | PASS |
Jack Reynolds
|
|
|
rough-final for a temporary occupancy. All exhaust fans are in, expect kitchen hoods. dryer vents are in, and GDRS are in. Gas lines are NOT done and gas lines has been pushed back GC doesnt need them right now. Phone #: ###-#### Inspection requested via web by adrian manzo - R/I ok
|
Final | 8/16/2019 | 8/16/2019 | 8/16/2019 | A | PART |
Jack Reynolds
|
|
|
rough-final for a temporary occupancy. All exhaust fans are in, expect kitchen hoods. dryer vents are in, and GDRS are in. Gas lines are NOT done and gas lines has been pushed back GC doesnt need them right now. Phone #: ###-#### Inspection requested via web by adrian manzo - partial final ok - signed temp occ
|
Rough-in | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | PASS |
Jack Reynolds
|
|
|
duct Insulation inspection Phone #: ###-#### Inspection requested via web by adrian manzo - duct insulation ok - ceiling cover ok will come back through and check ceiling diffusers and bathroom exhaust fans when completed and tied in - still need to check kitchen hood venting, dryer venting, and added gas line
|
Conference | 8/13/2019 | 8/13/2019 | 8/13/2019 | P | DONE |
Jack Reynolds
|
|
|
GC (ESI) requested conf with plm & mech inspector // Marvin Phone #: ###-#### - Talked with Marvin the GC about whats needed from the mech contractor for temps -
|
Rough-in | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | PASS |
Jack Reynolds
|
|
|
Rough-in for rest of the all duct work and seal inspection. Phone #: ###-#### Inspection requested via web by adrian manzo - duct seal on the rest of the building ok - ok for duct insulation - exhaust fans will be done by next inspection - dryer vents will be going out building sidewall below ceiling estimate of 6-8' of duct per the general - range hoods are going to be changed to 200 cfm each per the general - dishwasher hood will not be needed since appliance manufacture specs dont require it per the general. will need those installation instructions on side for inspecting
|
Rough-in | 8/7/2019 | 8/8/2019 | 8/8/2019 | A | PASS |
Jack Reynolds
|
|
|
Would like a duct work rough-in for some of the unit spaces. Space # 6852,6854,; 6858 Phone #: ###-#### Inspection requested via web by adrian manzo - duct seal ok on north side units -ok for duct insulation - still need to see exhaust fan installation in laundry room
|
Conference | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | DONE |
Jack Reynolds
|
|
|
Want to meet on duct work questions about existing duct work/flex we are not changing. Phone #: ###-#### Inspection requested via web by adrian manzo
|
Issue PAID IN FULL permit | | | 7/11/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/11/2019 | | DONE |
|
|
|
This permit was created on the web by adrian manzo
|