Final | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Jack Reynolds
|
|
|
Doors are unlocked, ready anytime. Call me if you need. ###-#### Thanks, Floyd Inspection requested via web by Floyd Floyd Peek -final ok
|
Final | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | FAIL |
Jack Reynolds
|
|
|
door will be unlocked. Call Max with any concerns Phone #: ###-#### Inspection requested via web by Floyd Floyd Peek - 2203 was unlocked but needs duct blast reports onsite -2201 was locked unsure of duct blast report
|
Final | 10/1/2019 | 10/1/2019 | 10/1/2019 | A | CANC |
Jack Reynolds
|
|
|
Doors are unlocked >> Inspection requested via web by Floyd Floyd Peek Inspection cancelled from web by: Floyd Floyd Peek
|
Rough-in | 7/30/2019 | 7/30/2019 | 7/30/2019 | A | PASS |
Jack Reynolds
|
|
|
Inspection requested via web by Floyd Floyd Peek 2- 5lb flue pressure tests ok 2-20lb gas pressure tests ok - tagged meter location -R/I ok
|
Rough-in | 7/29/2019 | 7/29/2019 | 7/29/2019 | P | FAIL |
Jack Reynolds
|
|
|
Inspection requested via web by Floyd Floyd Peek - dryer and exhaust fan terminations need moved out past the party wall - supply trunks in crawl need insulated - return cans in attic need insulated - south side 5lb flue pressure test fail - combustion air into mech rooms needs deleted
|
Pressure Test | 7/29/2019 | 7/29/2019 | 7/29/2019 | P | FAIL |
Jack Reynolds
|
|
|
Inspection requested via web by Floyd Floyd Peek 2- 20lb gas pressure test ok - tagged meter locations 1- northside 5lb flue pressure test ok - south side 5lb flue pressure test fail
|
Issue PAID IN FULL permit | | | 7/29/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/29/2019 | | DONE |
|
|
|
This permit was created on the web by Floyd Floyd Peek
|