Final | 10/9/2019 | 10/9/2019 | 10/9/2019 | P | PASS |
Troy James
|
|
|
|
Final | 10/8/2019 | 10/8/2019 | 10/8/2019 | A | PART |
Brian Scoles
|
|
|
need secure all new gas piping to supports on roof- all equipment needs set into working order under class 1 hood
|
Final | 9/27/2019 | 10/1/2019 | 10/1/2019 | A | CANC |
Brian Scoles
|
|
|
JOB CONTACT - AB ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- bld under review- need plan mod excepted and new approved prints from plan mod onsite for inspection
|
Rough-in | 8/26/2019 | 8/27/2019 | 8/27/2019 | A | PASS |
Brian Scoles
|
|
|
AUSTIN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- 60lb gas test whole system from kitchen to roof ok- need documentation from engineer stating ok to use compression fitting for tie in on existing line since upgrading to 5lb system and have onsite to view by final
|
Rough-in | 8/5/2019 | 8/6/2019 | 8/6/2019 | P | PASS |
Brian Scoles
|
|
|
ALAN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- R/I ok- ok to cover
|
Pressure Test | 8/6/2019 | 8/6/2019 | 8/6/2019 | A | PASS |
Brian Scoles
|
|
|
ALAN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- 60lb gas pass in kitchen wall behind cook line to roof
|
Issue PAID IN FULL permit | | | 8/5/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/5/2019 | | DONE |
|
|
|
This permit was created on the web by BECCA DUMMER
|
First Notice | 10/9/2019 | 10/9/2019 | | | |
Troy James
|
|
|
|