Final | 8/21/2019 | 8/22/2019 | 8/22/2019 | P | PASS |
Brian Scoles
|
|
|
final Phone #: ###-#### Inspection requested via web by Brandon Sorensen- final ok
|
Final | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PART |
Brian Scoles
|
|
|
FINAL - CALL TONY Phone #: ###-#### Inspection requested via web by Brandon Sorensen- square to round in attic needs insulation finshed- luminare in attic needs installed in attic- platform installed
|
Rough-in | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Brian Scoles
|
|
|
tony - sealer inspection Phone #: ###-#### Inspection requested via web by Brandon Sorensen- seal on duct in attic ok- ok to insulate- need 30 inch wide platform installed at electric heater for servicing platform by final- need to see insulation at final
|
Issue PAID IN FULL permit | | | 8/19/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/19/2019 | | DONE |
|
|
|
This permit was created on the web by Brandon Sorensen
|
First Notice | 8/22/2019 | 8/22/2019 | | | |
Brian Scoles
|
|
|
|