Final | 10/9/2019 | 10/9/2019 | 10/9/2019 | P | PASS |
Troy James
|
|
|
Plans are on site, equipment is set and fire system is getting its final this afternoon. Phone #: ###-#### Inspection requested via web by Drew Tverdy
|
Final | 10/8/2019 | 10/8/2019 | 10/8/2019 | A | PART |
Brian Scoles
|
|
|
Emailing balance report to Brian. Phone #: ###-#### Inspection requested via web by Drew Tverdy- all equipment needs set into working order under class 1 hood and maintain 6" clearance on all sides of appliance and all moveable appliances tethered- need to install SS panel north end of hood- air balance report ok- still need approved plan mod drawings onsite to review them
|
Rough-in | 9/29/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Brian Scoles
|
|
|
Rough in before last piece of hood shroud goes on. Phone #: ###-#### Inspection requested via web by Drew Tverdy- MAU duct and seal above hood ok- ok for ss skirting panels to be installed above hood
|
Rough-in | 9/22/2019 | 9/23/2019 | 9/23/2019 | A | PASS |
Brian Scoles
|
|
|
Light test on hood to duct connection for final cover. Phone #: ###-#### Inspection requested via web by Drew Tverdy- light test at 2 locations to hoods ok- MAU intake needs plumbing vents/ water heater vent extended up 3 feet above inlet or 10 feet away- exhaust fans on roof ok
|
Rough-in | 9/18/2019 | 9/18/2019 | 9/18/2019 | P | PASS |
Brian Scoles
|
|
|
Light test in grease duct. Will be ready by 12:30 Phone #: ###-#### Inspection requested via web by Drew Tverdy- light test pass 2 drops- will look at final 4 welds when installed to hood and curb
|
Issue PAID IN FULL permit | | | 8/27/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 8/27/2019 | | |
|
|
|
|
Application received | | | 8/27/2019 | | DONE |
|
|
|
This permit was created on the web by Drew Tverdy
|
First Notice | 10/9/2019 | 10/9/2019 | | | |
Troy James
|
|
|
|