Final | 1/10/2020 | 1/13/2020 | 1/13/2020 | A | PASS |
Brian Scoles
|
|
|
GARI ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza- fireplace final ok
|
Rough-in | 11/5/2019 | 11/6/2019 | 11/6/2019 | A | PASS |
Brian Scoles
|
|
|
Gari ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza- fireplace R/I ok- met with GC about smurf tubing that didnt meet clearances and fire foam thats sprayed in on pipe to resolve this issue from here on out
|
Rough-in | 10/29/2019 | 10/30/2019 | 10/30/2019 | A | FAIL |
Brian Scoles
|
|
|
GARI ###-#### MANUAL UNDER UNIT W/REMOTE Phone #: ###-#### Inspection requested via web by Mike Almanza- draft stop to flue does not have 1" clearance to combustible- offset inside chase doesnt have 1" clearance to vertical 2x4
|
Issue PAID IN FULL permit | | | 10/10/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/10/2019 | | DONE |
|
|
|
This permit was created on the web by Mike Almanza
|