Print Statement | | | 1/24/2020 | | DONE |
|
|
|
|
Final | 1/16/2020 | 1/16/2020 | 1/16/2020 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige -final ok
|
Final | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige - A/C needs locking caps installed on service ports - secondary drain needs pvc extended down to floor
|
Rough-in | 11/21/2019 | 11/22/2019 | 11/22/2019 | A | PASS |
Ben Livingston
|
|
|
please call prior to arriving for access Phone #: ###-#### Inspection requested via web by Nicholas Paige - rough in pass - - flue and fresh air remain and will be expossed -
|
Issue PAID IN FULL permit | | | 11/14/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/8/2019 | | DONE |
|
|
|
This permit was created on the web by Nicholas Paige
|
First Notice | 1/16/2020 | 1/16/2020 | | | |
Jack Reynolds
|
|
|
|