Final | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Brian Scoles
|
|
|
Final Inspection. Please contact Daryl prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator- final ok- card signed
|
Final | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | PART |
Brian Scoles
|
|
|
Final inspection - Please contact Daryl prior to arrival. ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator- Temp occupancy ok- need to add 2 10" round dampers in OSA and Exhaust in unoccupied building and verify air balance to cfm shown on key note 2- Screening around units on roof need completed to verify access to doors are ok- talk with GC onsite
|
Issue PAID IN FULL permit | | | 11/19/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/19/2019 | | DONE |
|
|
|
This permit was created on the web by Commercial Coordinator
|
First Notice | 5/4/2020 | 5/4/2020 | | | |
Brian Scoles
|
|
|
|