Final | 1/10/2020 | 1/13/2020 | 1/13/2020 | A | PASS |
Brian Scoles
|
|
|
call acess- Tim Phone #: ###-####- final ok- equipment set in place
|
Pressure Test | 11/25/2019 | 11/25/2019 | 11/25/2019 | P | PASS |
Brian Scoles
|
|
|
Tim Phone #: ###-####- 20lb gas pass- will need access door installed in ceiling by final to access main gas shutoff valve- all 4 shutoff valves will need sediment traps installed after shut offs and before appliances- equipment may need tethers by final also
|
Pressure Test | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | FAIL |
Brian Scoles
|
|
|
Tim Phone #: ###-#### PLEASE CALL FOR ACCESS- gauge below 20psi- need 2 shutoff valves with open tee between them- single shutoff valve can not have air one side and gas other- need roof access- schedule when ready
|
Application received | | | 11/20/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/20/2019 | | DONE |
|
|
|
|
First Notice | 1/13/2020 | 1/13/2020 | | | |
Brian Scoles
|
|
|
|