Final | 12/30/2019 | 12/31/2019 | 12/31/2019 | P | PASS |
Chad Schwendiman
|
|
|
Roof access ladder is installed (permanent ladder) Phone #: ###-#### Inspection requested via web by Kelli Morgan
|
Final | 12/4/2019 | 12/5/2019 | 12/5/2019 | A | PART |
Jack Reynolds
|
|
|
Gas connections, 4-heaters on roof and 2- heaters suspended in shop areas Phone #: ###-#### Inspection requested via web by Kelli Morgan - partial final on gas piping need access to roof
|
Rough-in | 12/1/2019 | 12/2/2019 | 12/2/2019 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Kelli Morgan - gas line R/I ok - pressure tests ok
|
Pressure Test | 12/2/2019 | 12/2/2019 | 12/2/2019 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Kelli Morgan 3- 20lb gas pressure test ok tagged meters
|
Pressure Test | 12/1/2019 | 12/2/2019 | 12/1/2019 | P | CANC |
Jack Reynolds
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kelli Morgan Inspection cancelled from web by: Kelli Morgan
|
Rough-in | 11/27/2019 | 11/29/2019 | 11/29/2019 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Kelli Morgan - need to see 10 mill tape installed on piping all the way through penetration. leave penetration seal off so 10 mill tape can be verified - re test when ready
|
Rough-in | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Kelli Morgan - low pressure test should be on a 30lb gauge at 20lb - all gas line penetrations to the outdoors need a protective coating installed. roof and wall penetrations - re test when ready
|
Issue PAID IN FULL permit | | | 11/26/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/26/2019 | | DONE |
|
|
|
This permit was created on the web by Kelli Morgan
|
First Notice | 12/31/2019 | 12/31/2019 | | | |
Chad Schwendiman
|
|
|
|