Final | 4/29/2020 | 4/29/2020 | 4/29/2020 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Jose Lagunas - final ok
|
Rough-in | 2/24/2020 | 2/24/2020 | 2/24/2020 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Jose Lagunas - R/I ok - equipment not set at R/I check at final
|
Pressure Test | 2/24/2020 | 2/24/2020 | 2/24/2020 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Jose Lagunas - 5lb flue pressure test ok - 20lb gas pressure test ok - tagged meter location
|
Rough-in | 2/18/2020 | 2/18/2020 | 2/18/2020 | P | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Jose Lagunas - need approved ManJ onsite - line set needs R/I - gas gauge would not zero - 5lb flue test needs to be on a 15lb gauge - water heater bvent does not fit into 2x4 wall - supply cans in floor above garage need insulated - combustion air openings are not big enough for water heater and furnace
|
Issue PAID IN FULL permit | | | 2/14/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/14/2020 | | DONE |
|
|
|
This permit was created on the web by Jose Lagunas
|