Final | 6/29/2020 | 6/30/2020 | 6/30/2020 | A | PART |
Jack Reynolds
|
|
|
Please call Dustin at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - final on BLD B only ok - signed temp occ for BLD B - need to pull permit for BLD C when installing starts
|
Rough-in | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Jack Reynolds
|
|
|
Please call Dustin at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - R/I ceiling cover ok
|
Rough-in | 6/19/2020 | 6/22/2020 | 6/22/2020 | A | FAIL |
Jack Reynolds
|
|
|
Please call Dustin at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - finish insulation on fresh air ducts - support flex ducting
|
Rough-in | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | PASS |
Jack Reynolds
|
|
|
Please call Dustin at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - duct seal on fresh air duct to indoor head ok for insulation - extended duct runs duct seal ok for insulation - condensate line tie in to indoor head ok - breeze way ducted split system duct seal ok for insulation
|
Rough-in | 4/30/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Jack Reynolds
|
|
|
Please call Dustin at least 30 min prior to inspection, he is ready to do video if needed, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - bathroom and common hallway hard lid cover ok. three locations need insulation finished but can be seen through drop ceiling at next R/I inspection - walked through and checked line set runs from BS box to indoor head locations - condensate mains ok but still need connected to indoor units
|
Rough-in | 3/30/2020 | 3/31/2020 | 3/31/2020 | A | PASS |
Jack Reynolds
|
|
|
Please call Dustin at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - R/I duct seal ok for insulation
|
Rough-in | 3/23/2020 | 3/24/2020 | 3/24/2020 | A | PART |
Jack Reynolds
|
|
|
Please call Matt at least 30 min prior to inspection, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum - bathroom hard lid duct seal ok for insulation
|
Rough-in | 3/10/2020 | 3/11/2020 | 3/11/2020 | A | PART |
Jack Reynolds
|
|
|
A partial rough-in on Bldg B. Please call Matt prior to arrival. Matt:###-####.Thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum - partial R/I on 3 returns located in wall duct seal ok
|
Issue PAID IN FULL permit | | | 2/28/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/28/2020 | | DONE |
|
|
|
This permit was created on the web by Rhonda Marcum
|