Final | 7/13/2020 | 7/14/2020 | 7/14/2020 | P | PASS |
Jack Reynolds
|
|
|
Final Phone #: ###-#### Inspection requested via web by Brandon Sorensen
|
Rough-in | 6/5/2020 | 6/8/2020 | 6/8/2020 | A | PASS |
Jack Reynolds
|
|
|
cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen - R/I ceiling cover ok
|
Rough-in | 4/22/2020 | 4/24/2020 | 4/24/2020 | A | PASS |
Jack Reynolds
|
|
|
Rough in - call matt or Brandon Phone #: ###-#### Inspection requested via web by Brandon Sorensen - R/I ok duct seal ok for insulation - Talked with Matt,General contractor and roof contractor about b vent clearances and the plan to maintain 1" clearances with roof wrap. -1" clearances to roof insulation and below ok
|
Rough-in | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PART |
Jack Reynolds
|
|
|
hard lid cover for bathrooms Phone #: ###-#### Inspection requested via web by Brandon Sorensen - bathroom hard lid partial R/I ok - unit heaters b vent through roof will need 1" clearances
|
Issue PAID IN FULL permit | | | 3/5/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/5/2020 | | DONE |
|
|
|
This permit was created on the web by Brandon Sorensen
|
First Notice | 7/14/2020 | 7/14/2020 | | | |
Jack Reynolds
|
|
|
|