First Notice | 6/22/2020 | 6/22/2020 | 6/30/2020 | | DONE |
Jack Reynolds
|
|
|
This permit finaled on the web by Stacia Haumann
|
Final | 6/19/2020 | 6/22/2020 | 6/22/2020 | A | PASS |
Jack Reynolds
|
|
|
If questions call Nolan @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Pressure Test | 5/1/2020 | 5/1/2020 | 5/1/2020 | P | PASS |
Jack Reynolds
|
|
|
If Questions call Nolan @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann - 60lb gas test ok - inner gate was locked and couldn't inspection gas lines installed. Will walk with contractor at suite 140 pressure test to inspect lines. - tagged meter location
|
Issue PAID IN FULL permit | | | 3/16/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/12/2020 | | DONE |
|
|
|
This permit was created on the web by Stacia Haumann
|