Final | 6/1/2020 | 6/1/2020 | 6/1/2020 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Tim Petsche- final ok- air balance ok- no card onsite
|
Card not on site to sign | 6/1/2020 | 6/1/2020 | 6/1/2020 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Tim Petsche- card no onsite
|
Final | 5/27/2020 | 5/28/2020 | 5/28/2020 | A | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Tim Petsche- need air balance report onsite or send to bscoles@cityofboise.org- temp occupancy ok- no occupancy card onsite to sign
|
Final | 5/25/2020 | 5/26/2020 | 5/26/2020 | A | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Tim Petsche - Need to install outside air hoods ob RTU's and have the system balanced
|
Final | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Tim Petsche- dryer ducting needs 6" clearance to combustibles at roof 2012 IMC 504.7- dryer installations instruction do not address clearances- GC is aware of issues- need roof access at final- still need engineer approval for ducting installed that different thsn approved prints-
|
Rough-in | 4/10/2020 | 4/13/2020 | 4/13/2020 | A | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Tim Petsche- hard lids ok to cover- need engineers approval for the way ducting ran doesnt match approved drawing- need engineer stamped approval onsite before next inspection for the way ducts installed
|
Issue PAID IN FULL permit | | | 3/30/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/30/2020 | | DONE |
|
|
|
This permit was created on the web by Tim Petsche
|
First Notice | 6/1/2020 | 6/1/2020 | | | |
Brian Scoles
|
|
|
|