Final | 6/18/2020 | 6/18/2020 | 6/18/2020 | P | PASS |
Jack Reynolds
|
|
|
Mechanical Final Inspection needed for Cafe Rio Air Balance Report will be sent to Jack Reynolds. If you need anything please contact Karl at ###-#### Phone #: ###-#### Inspection requested via web by Karl Hestekin - final ok
|
Final | 6/10/2020 | 6/11/2020 | 6/11/2020 | P | CANC |
Jack Reynolds
|
|
|
Partial- Above grid insp. Phone #: ###-#### Inspection requested via web by Karl Hestekin - should have been R/I ceiling cover inspection
|
Rough-in | 6/11/2020 | 6/11/2020 | 6/11/2020 | P | PASS |
Jack Reynolds
|
|
|
Partial- Above grid insp. Phone #: ###-#### Inspection requested via web by Karl Hestekin - R/I ceiling cover ok
|
Rough-in | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PART |
Jack Reynolds
|
|
|
Mechanical Duct Seal Inspection needed at Cafe Rio If you have any questions please contact Karl ###-####,Thank you. Phone #: ###-#### Inspection requested via web by Karl Hestekin - partial R/I duct seal ok for insulation
|
Rough-in | 5/12/2020 | 5/13/2020 | 5/13/2020 | A | PART |
Jack Reynolds
|
|
|
Mechanical Cover Inspection needed for Cafe Rio. Please contact Mike Sagars with any questions ###-####. Phone #: ###-#### Inspection requested via web by Karl Hestekin - bathroom hardlid R/I cover ok
|
Conference | 5/12/2020 | 5/13/2020 | 5/13/2020 | A | DONE |
Jack Reynolds
|
|
|
Mechanical Conference Inspection needed for Cafe Rio please contact Mike Sagars at ###-####, thank you. Phone #: ###-#### Inspection requested via web by Karl Hestekin - one small hood on the west side needs wall construction to maintain clearances based on exception in code section from the IMC 507.9
|
Fees Due Hold | 5/8/2020 | | 5/12/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/21/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/21/2020 | | DONE |
|
|
|
This permit was created on the web by Karl Hestekin
|
First Notice | 6/18/2020 | 6/18/2020 | | | |
Jack Reynolds
|
|
|
|