Final | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Brian Scoles
|
|
|
access 1027 Phone #: ###-#### Inspection requested via web by David Nelson- final ok- no card onsite
|
Card not on site to sign | 6/24/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Brian Scoles
|
|
|
access 1027 Phone #: ###-#### Inspection requested via web by David Nelson- no card onsite
|
Rough-in | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PART |
Brian Scoles
|
|
|
access 1027 Phone #: ###-#### Inspection requested via web by David Nelson- seal on duct ok- ok to insulate- call i when insulation and registers are completed to pass R/I- need to address valuation and pay fees for phase 2 by final inspection
|
Telephone call | | | 6/3/2020 | | DONE |
|
|
|
Spoke with Mindy from 45th Parallel Electric, she informed us the value and scope of work changed. See new 306 in documents.
|
Rough-in | 4/30/2020 | 5/1/2020 | 5/1/2020 | P | PART |
Brian Scoles
|
|
|
access 1027 Phone #: ###-#### Inspection requested via web by David Nelson- temp occupancy phase 1 final ok on 2 exam rooms- ok for ceiling tiles- need to review valuation on job and update for phase 2
|
Final | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | CANC |
Brian Scoles
|
|
|
Final ; final grid inspection Phone #: ###-#### Inspection requested via web by David Nelson- should have been R/I inspection
|
Rough-in | 4/30/2020 | 4/30/2020 | 4/30/2020 | A | FAIL |
Brian Scoles
|
|
|
Final ; final grid inspection Phone #: ###-#### Inspection requested via web by David Nelson- seal on ducting ok- need to insulate supply ducting above grid in the 2 exam rooms- flex and registers ok- need right suite number listed for inspection no 120 present
|
Issue PAID IN FULL permit | | | 4/29/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 4/29/2020 | | |
|
|
|
|
Application received | | | 4/29/2020 | | DONE |
|
|
|
This permit was created on the web by David Nelson
|
First Notice | 6/24/2020 | 6/24/2020 | | | |
Brian Scoles
|
|
|
|