Final | 7/2/2020 | 7/6/2020 | 7/6/2020 | A | PASS |
Jack Reynolds
|
|
|
Inspection requested via web by Steve Torgerson - building shell and core final ok
|
Miscellaneous action | | | 5/13/2020 | | DONE |
|
|
|
reduced valuation by $84,264 per attached memo from applicant. Value now accounted for under MEC20-01856. Refund to be issued for overpayment received.
|
Rough-in | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | FAIL |
Jack Reynolds
|
|
|
Seal inspection on ductwork in office area. Phone #: ###-#### Inspection requested via web by Steve Torgerson - duct seal fail finish duct seal and re schedule
|
Issue PAID IN FULL permit | | | 5/7/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/7/2020 | | DONE |
|
|
|
This permit was created on the web by Steve Torgerson
|
First Notice | 7/6/2020 | 7/6/2020 | | | |
Jack Reynolds
|
|
|
|