Final | 6/26/2020 | 6/26/2020 | 6/26/2020 | P | PASS |
Jack Reynolds
|
|
|
final reinspect water heater vent and ductless AC Phone #: ###-#### Inspection requested via web by Steve Torgerson - final ok
|
Conference | 6/25/2020 | 6/25/2020 | 6/25/2020 | A | FAIL |
Jack Reynolds
|
|
|
I will leave the air balance report with the Superintendent Rod Baxter Cell ###-#### Phone #: ###-#### Inspection requested via web by Steve Torgerson - ductless split jacket MC cable needs an approved UL listed connector - water heater venting needs approved PVC installed. celluarcore pvc is prohibited - PVC termination needs to be 12" above roof line
|
Rough-in | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | PASS |
Chad Schwendiman
|
|
|
inspect duct insulation for cover inspection. Phone #: ###-#### Inspection requested via web by Steve Torgerson - Okay to cover ceiling
|
Rough-in | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Torgerson - R/I duct seal ok for insulation
|
Rough-in | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | FAIL |
Jack Reynolds
|
|
|
re-inspect ductwork to cover. Phone #: ###-#### Inspection requested via web by Steve Torgerson - duct seal on exhaust trunk line needs sealed - one start collar is being blocked by framing and needs sealed
|
Issue PAID IN FULL permit | | | 5/14/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/11/2020 | | DONE |
|
|
|
This permit was created on the web by Steve Torgerson
|
First Notice | 6/26/2020 | 6/26/2020 | | | |
Jack Reynolds
|
|
|
|