Rough-in | 8/6/2020 | 8/10/2020 | 8/10/2020 | A | FAIL |
Brian Scoles
|
|
|
cover / rough Phone #: ###-#### Inspection requested via web by Brandon Sorensen- still need 12" OSA ran per key note 6 or get engineer letter of approval for the way system is installed- registers and flex ok- cover for ceiling will be ok when OSA is addressed- no GC onsite to talk to
|
Rough-in | 7/21/2020 | 7/22/2020 | 7/22/2020 | A | PASS |
Brian Scoles
|
|
|
hard lid inspection Phone #: ###-#### Inspection requested via web by Brandon Sorensen- R/I ok- hard lids ok to cover- need to address 12" OSA thats shown on approved drawingsthat hasnt been ran yet- talked to installer about this to touch basis with engineer will need info by final inspection
|
Rough-in | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | FAIL |
Brian Scoles
|
|
|
Josh ###-####. Phone #: ###-#### Inspection requested via web by Brandon Sorensen- need city approved prints onsite for inspection- seal on misc duct ok ok to insulate- need plenum rated insulation-
|
Issue PAID IN FULL permit | | | 7/8/2020 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/8/2020 | | DONE |
|
|
|
This permit was created on the web by Brandon Sorensen
|
Final | 8/13/2020 | 8/14/2020 | | A | |
Brian Scoles
|
|
|
final Phone #: ###-#### >> Inspection requested via web by Brandon Sorensen
|