INSP - Final | 4/16/1996 | 4/17/1996 | 4/18/1996 | A | PASS |
Wes Worcester
|
|
|
|
INSP - Final | 4/16/1996 | 4/17/1996 | 4/18/1996 | A | PASS |
Wes Worcester
|
|
|
|
Issue PAID IN FULL permit | | | 1/17/1996 | | |
|
|
|
|
INSP - Gas pressure test | 1/3/1996 | 1/3/1996 | 1/3/1996 | P | PASS |
Alan Hauser
|
|
|
01/03/96 350 - REINSPECTION PRESSURE TEST OK GAS PIPING OK #29966
|
INSP - Rough-in & Gas Pressure | 12/27/1995 | 12/28/1995 | 1/2/1996 | A | FAIL |
Alan Hauser
|
|
|
12/27/95 350 - PRESSURE TEST FAILED FOR THE 3RD TIME, CALLED WESTERN AND TALKED TO THEM ABOUT IT AND TOLD THEM TO SOAP THE LINE GOOD AND STAY TIL LEAK IS FOUND
|
INSP - Framing/ Rough-in | 12/28/1995 | 12/28/1995 | 12/28/1995 | | FAIL |
Dave Lightfoot
|
|
|
/ / 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED gas test fail RFC -REINSPECT
|
INSP - Framing/ Rough-in | 12/28/1995 | 12/28/1995 | 12/28/1995 | | FAIL |
Dave Lightfoot
|
|
|
/ / 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED gas test fail RFC -REINSPECT
|
INSP - Framing/ Rough-in | 12/28/1995 | 12/28/1995 | 12/28/1995 | | FAIL |
Dave Lightfoot
|
|
|
/ / 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED gas test fail RFC -REINSPECT
|
INSP - Framing/ Rough-in | 12/28/1995 | 12/28/1995 | 12/28/1995 | | FAIL |
Dave Lightfoot
|
|
|
/ / 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED gas test fail RFC -REINSPECT
|
INSP - Rough-in & Gas Pressure | 12/21/1995 | 12/22/1995 | 12/22/1995 | A | PART |
Alan Hauser
|
|
|
12/21/95 350 - ROUGH-IN IS OK PRESSURE TEST FAILED
|
Issue FEE-DUE permit | | | 12/21/1995 | | FEE |
|
|
|
|
Application received | | | 12/21/1995 | | |
|
|
|
|