INSP - Final | 10/1/1996 | 10/1/1996 | 10/1/1996 | P | PASS |
|
|
|
10/01/96 326 - Work completed. Final ok.
|
INSP - Final | 10/1/1996 | 10/1/1996 | 10/1/1996 | P | PASS |
|
|
|
10/01/96 326 - Work completed. Final ok.
|
INSP - Final | 9/5/1996 | 9/5/1996 | 9/5/1996 | P | PASS |
|
|
|
09/05/96 326 - Partial Final ok few items to complete. Signed Temp. Occu Final next week.
|
INSP - Final | 9/5/1996 | 9/5/1996 | 9/5/1996 | P | PASS |
|
|
|
09/05/96 326 - Partial Final ok few items to complete. Signed Temp. Occu Final next week.
|
INSP - Framing/ Rough-in | 7/23/1996 | 7/23/1996 | 7/23/1996 | P | PASS |
Dave Lightfoot
|
|
|
07/23/96 337 - R/I FOR WEST END OK
|
INSP - Framing/ Rough-in | 6/18/1996 | 6/18/1996 | 6/18/1996 | | PASS |
Dave Lightfoot
|
|
|
/ / 337 - REINSPECTION 2 EXISTING MECH ROOMS OK
|
INSP - Framing/ Rough-in | 6/17/1996 | 6/18/1996 | 6/17/1996 | A | |
|
|
|
FOR THE MECHANICAL ROOM - MIKE ###-####-JOB ####-#### FOR ACCESS
|
INSP - Framing/ Rough-in | 6/11/1996 | 6/11/1996 | 6/11/1996 | | PART |
Dave Lightfoot
|
|
|
/ / 337 - RGHN-OK ROUGH IN
|
INSP - Framing/ Rough-in | 6/10/1996 | 6/11/1996 | 6/10/1996 | A | |
|
|
|
PARTIAL R/I SOUTHSIDE
|
Issue PAID IN FULL permit | | | 4/17/1996 | | |
|
|
|
|
INSP - Framing/ Rough-in | 4/11/1996 | 4/11/1996 | 4/11/1996 | P | PASS |
|
|
|
04/11/96 326 - NORTH SIDE OF BUILDING Ductwork R/I (north side existing bldg.) - ok.
|
INSP - Framing/ Rough-in | 3/7/1996 | 3/7/1996 | 3/7/1996 | P | PASS |
|
|
|
03/07/96 326 - Partial R/I ok.
|
Application received | | | 2/7/1996 | | |
|
|
|
|
Issue FEE-DUE permit | | | 2/7/1996 | | FEE |
|
|
|
|