INSP - Final | 9/23/1996 | 9/24/1996 | 9/24/1996 | A | NR |
Wes Worcester
|
|
|
|
INSP - Final | 9/23/1996 | 9/24/1996 | 9/24/1996 | A | NR |
Wes Worcester
|
|
|
|
INSP - Gas pressure test | 7/29/1996 | 7/29/1996 | 7/29/1996 | | FAIL |
Alan Hauser
|
|
|
/ / 350 - PRESSURE DOWN AND NEEDS TO CHANGE TEE AT FURN. W/H
|
INSP - Gas pressure test | 7/26/1996 | 7/29/1996 | 7/29/1996 | A | PASS |
Alan Hauser
|
|
|
07/29/96 350 - P/T OK #28216
|
Issue PAID IN FULL permit | | | 7/26/1996 | | |
|
|
|
|
INSP - Rough-in & Gas Pressure | 7/25/1996 | 7/25/1996 | 7/25/1996 | P | PART |
Alan Hauser
|
|
|
07/25/96 350 - R/I OK FOR DUCT BUT GAS PIPE IS UNDERSIZED FOR WHOLE HOUS PIPE SHOULD START OUT 11/4"
|
INSP - Conference | 7/25/1996 | 7/25/1996 | 7/25/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - talked to builder and heating contractor about job
|
Application received | | | 7/25/1996 | | |
|
|
|
|
Issue FEE-DUE permit | | | 7/25/1996 | | |
|
|
|
|